Sanibel Causeway & Bridge Construction Project
HomeOverviewProject NewsToll PlazaPhotos/GraphicsSafetyScheduleFAQsContact Us
project_thumb Sanibel Causeway Project


 

  Bridge Building 101


·  First yellow floating turbidity barriers are put in place in the water to retain any suspended sediment (water flows through barriers, more dense sediment remains) with silt fence on the land, for the same purpose.

·  
Barge(s) are brought in with the crane and pile-driver.

·  In some cases, sheet piles (sheets of steel) are temporarily installed to prevent erosion of the bank.

·  Test piles are driven to determine the length of the piles. Pile driving analysis done by engineers during the driving determines length of the permanent piles.

·  Permanent piles are driven once a determination of required length is made. Piles are cast at a concrete plant, barged in and then driven into ground. Approximately 2 to 4 piles are driven per day.

·  The footings are formed and poured at the casting yard (precast) then barged to the Causeway and placed on top of the piles.

·  The piers are also precast, barged to the site and erected on top of the footing.

·  The precast beams are cast at the concrete plant and barged in and set in place on top of the piers.

·  The deck is formed and poured in place on top of the beams.

·  Cosmetics and drainage work is then completed.

·  Voila! You have a bridge!

cross section

Interesting Facts

Facts

Span information
· Bridge A has 19 spans @ 144’ and 2 spans @ 130'
· Bridge B has 13 spans @ 144’
· Bridge C has 26 spans @ 144’ and 1 span @ 120’

Height of bridges
· Bridge A clearance at center span: 70’ at Mean High Water.
· Bridge B height: Varies slightly in accord to geometry of the bridge.
· Bridge C height: Varies in accord to geometry of the bridge. Has a navigable channel of 26'.

Footings
· For Bridge A all water footings except one are composed of twenty-one (21) 30" pre-cast concrete piles.
· For Bridges B & C the water footings are composed of fifteen (15) 30" pre-cast concrete piles.

Footing configuration
· Bridge A basic footing configuration: 49’-6"’ X 19’6" X 6’
· Bridge B basic footing configuration: 36’ X 21’ X 6’.
Pre-cast weight of footing: 303 tons.
Average weight of pre-cast piers: 190,000 Lbs.
· Bridge C Basic footing configuration: 36’ X 21’ X 6’.
Pre-cast weight of footing: 303 tons.

Ship impact bridges will be able to sustain: 1 kip = 1000 Lbs.
· Bridge A will be able to sustain a maximum ship impact force of 1200 kips (1.2 million Lbs). The balance of ship impact that the remainder of the footings will be able to sustain is 800 kips (800,000 Lbs) on average.
· Bridges B & C will be able to sustain a maximum ship impact force of 200 kips (200,000 Lbs