Construction
Commences
Construction has begun to replace the bridges at the Sanibel
Causeway. Project completion is estimated for Fall 2007.

Construction
Sequence
Construction began with Bridge B (the middle bridge) in
August 2004. Construction of Bridge A (adjacent to the mainland)
began in January 2005 and will be followed by construction of
Bridge C (adjacent to Sanibel) beginning in July 2005, more
information can be found on the
Schedule web
page. The construction will initially begin with pile driving
efforts adjacent to the existing bridge(s). Following this,
substructure components (such as footings and foundations) and then
girders (beams) will be installed for each section/span of the
bridge. The concrete deck will then be poured. Temporary roadways
on the causeway islands will be constructed concurrently to
coordinate and support the approach work to the Islands. Upon
bridge completion, final road and tie-in(s) will be
constructed.

Bridge A
Bridge A (the bridge adjacent to the mainland) will be a 70-foot
vertical clearance fixed span bridge. The new bridge typical
section includes two 12-foot (ft.) travel lanes, two 8 ft.
shoulders, open rails, and no sidewalks. The overall width of the
bridge is 43 ft. An alignment 10 ft. eastof the existing bridge was
selected. The fixed span bridge gives 70 feet of navigational
clearance and eliminates the need for scheduled openings, it also
allows for free flow of automobile and boat traffic.
Bridge B
The existing Bridge B (the middle bridge) is structurally in the
worst condition of the three bridges, having a low profile that
subjects the entire substructure and superstructure to salt spray.
The new bridge typical section includes two 12-foot (ft.) travel
lanes, two 8 ft. shoulders, open rails, and no sidewalks. The
overall width of the bridge is 43 ft. An alignment 10 ft. west of
the existing bridge was selected. In conjunction with an east
alignment for Bridge C (adjacent to Sanibel), this alignment avoids
impacts to the weigh station and restrooms on Island B. The bridge
profile will be raised a minimum of 4 ft. to raise the
superstructure above
the splash
zone.
Bridge C
Bridge C (bridge nearest to Sanibel) will be a 26 - foot vertical
clearance fixed span bridge.
The new bridge typical section includes two 12 ft. travel lanes,
two 8 ft. shoulders, and no sidewalks. The overall width of the
bridge is 43 ft. An alignment 10 ft. east of the existing bridge
was selected to avoid impacts to the weigh station and restrooms on
Island B, as well as to minimize impacts to the Sanibel Boat Ramp.
The new bridge will not impact the boat ramps, boat ramp parking
lot, or park entrance. All superstructure components will be
located above the splash zone. The existing bridge approaches will
be removed and the land
made available for recreational use.
Information on Precast Yard Operations on San Carlos Island
Lee County has granted a Limited
Development Order on the County’s San Carlos Island parcel
(formerly known as the Murphy Oil property) to Boh Brothers to
fabricate concrete components for the new Sanibel Causeway
bridges. Early next
month, the contractor will use a portion of the County’s
property (adjacent to Kelly Brothers property) as a temporary
concrete casting yard. The anticipated hours of operation for
the concrete fabrication activities will be Monday through Friday,
7 a.m. to 6 p.m. Concrete
fabrication activities are expected to be complete in the
Summer of
2006.
Concrete will
be delivered by concrete mixing trucks. No concrete will be mixed on
site. It is anticipated that concrete
trucks will deliver concrete two
to three days per week. On
these days, the trucks will deliver periodically from approximately
7 a.m. to 1 p.m. In season,
the contractor will base their hours of operation based on their
ability to get the concrete mixing trucks to the site in a timely
matter. Early morning and
late night deliveries may occur. In addition, during season, the
contractor will also coordinate the timing of deliveries with the
various cruise boat operations on the island. The contractor is coordinating
the timing of these deliveries with The Southwest Florida Marine
Institute (SFMI) buses and Trico Shrimp Company.
When delivered, the concrete will
be poured into a
series of three molds. As
the product cures, it will be staged on the property and
subsequently barged to the bridge site. Use of this property will result
in a cost savings due to its proximity to the project
site.
Several sabal palms may be relocated to other areas of the Lee
County site to provide additional landscape buffers to the
surrounding residences. The
concrete fabrication site will be fully fenced for safety and
security purposes.
County access to the existing boat ramp will remain open during the
construction period. All
necessary permits have been obtained by the contractor (fencing,
vegetation, etc.).
About the Project Team click here
|