Sanibel Causeway & Bridge Construction Project
HomeOverviewProject NewsToll PlazaPhotos/GraphicsSafetyScheduleFAQsContact Us
Sanibel Causeway Project Schedule Sanibel Causeway Project Schedule 


 

Schedule 


Sanibel Causeway Construction Schedule

 

SPAN

CONSTRUCTION OF NEW FACILITY

READY FOR TRAFFIC

DEMOLISH EXISTING STRUCTURE

A

January 2005

OPEN

October 2007

B

August 2004

OPEN

September 2007

C

July 2005

OPEN

September 2007


Completion of new Toll Plaza and ready for traffic - June 2007
Completion of new parking for Punta Rassa Boat Ramp - July 2007
Final completion of roadwork, drainage ponds, landscaping and seawalls –September 2007